Delivering One Job in Batches? Track What Arrived, Passed Review, and Is Still Missing

Use six spreadsheet columns to track what was agreed, delivered, reviewed, and carried forward. A hypothetical six-guide handover shows how to avoid double-counting.

JunProjects

A customer replies “Received” on LINE, and a colleague marks the entire job as complete in Excel. At the next handover, the team discovers that the message covered only the first batch, and some items are still waiting for review. Whenever a job can be delivered in parts, the tracking sheet should answer three questions: What was delivered this time? Who checked it? What remains open? Here is a method you can try in a spreadsheet.

Separate the agreement, the delivery, and the review

The original agreement says what you owe by the end of the job. Refer to the confirmed quotation or requirements version. The batch record says what you actually delivered on a particular day. The review record says who checked it, what criteria they used, and what passed. Sending an operating guide is a delivery. Having the person taking over follow that guide to complete an agreed task is an acceptance check. If the customer only acknowledges receipt, record it as received and awaiting review.

First decide which work needs multiple batches. Each batch should point to identifiable deliverables and a person authorized to review them. If two files can only be checked together, you can still deliver them separately, but keep the overall acceptance criteria. Two file transfers do not count as two passes. Likewise, if you send a corrected version of the same item on the same day, record the correction in the original batch.

Start with six columns in one spreadsheet

Use one row for each deliverable in a batch. If a batch contains two items that are checked differently, give each its own row and keep the same batch ID. Use the original item ID to link the summary to the batch records. Delivery dates, file transfers, and chat messages are poor substitutes for counting deliverables.

| Column | What to record | | --- | --- | | Batch and original item | Batch ID, item ID, and the applicable scope or quotation version. | | Planned delivery | The expected item or quantity and the acceptance criteria that apply. | | Actual delivery | The delivery date, what or how much was delivered, and a link to the file or version. | | Review result | Reviewer, review date, and outcome. Mark it as awaiting review when there is no result yet. If only part passed, specify which items. | | Outstanding items and reasons | Keep undelivered items, items awaiting review, and items needing correction separate. Count each item only once. | | Next action | Who will provide or check what, when to review it again, and which batch owns the follow-up. If the date is unknown, mark it as to be confirmed. |

Try working backward from a past job. Could someone taking over find the right files, tell which items were checked and which are waiting, and identify the batch that owns a correction using only this sheet? If the answer is still buried in someone's LINE conversation, fix the references or ownership before setting up reminders.

Hypothetical example: Six operating guides in two batches

A team agrees to deliver six operating guides, each with its own ID. It plans four for the first batch and delivers all four. The person taking over tries them as agreed: three pass, and one needs correction because a screen has changed and the steps no longer match. The other two are scheduled for the second batch and have yet to be delivered. The summary can now say: “Four delivered: three passed, one needs correction. Two not yet delivered.” Leave the first batch open. The guide that needs correction is already delivered, so it does not count as undelivered.

At the second delivery, record the revised guide under its original item ID in the first batch. Keep the new version, review date, and outcome. Record each of the two second-batch guides under its own ID and mark it as awaiting review once received. If the corrected guide passes, the job is now at four passed and two awaiting review. The number of times files were sent does not change the six agreed deliverables. If the customer asks for another guide, record it as a new request, assess the scope, and update the agreement after both sides confirm the change.

Ask three questions after each handover

  1. Can someone reconcile the totals without reading the chat? Count each agreed item once based on its current status. Keep prior entries so you can trace the changes.
  2. Who takes over each kind of open work? For example, the designated reviewer checks items awaiting review, the person who delivered an item corrects it, and the owner of the next batch confirms a date for undelivered work.
  3. Can we close the whole job? Once all batches are recorded, check the overall criteria and any exceptions. If the record also supports invoicing or maintenance handover, follow the applicable agreement. The spreadsheet status alone does not make that decision.

Pick one job that is often delivered in parts. Fill out the sheet using real, de-identified records, then ask the person delivering and the person taking over to read it separately. If they give different answers to “What is left?”, use the column where they disagree to start your next requirements discussion.

If your team wants to move this workflow out of Excel and LINE, see our custom management system service or start a proposal with one deliverable that tends to get missed. AI PM can help clarify roles, batches, and acceptance criteria and provide a preliminary estimate. Our team reviews and confirms the formal scope, quotation, delivery dates, and acceptance process with you. This is a planning example; actual deliverables follow what both sides agree to.