Before Going Live: Agree the Switch Plan and Handover Responsibilities
An accessible website is not the whole launch. Review versions, data, production connections, recovery and support, with seven readiness questions, a hypothetical project-tracking example and a switch-decision checklist.
The website opens. What else needs confirming?
The team has reviewed the test screens and is ready to move work out of Excel and LINE. The overlooked issue may be the handover rather than another feature: when does the old spreadsheet stop changing, what happens to late updates, and who helps users after launch?
Before going live, the business contact, actual users and delivery team should decide together whether the service is ready for the switch. Functional acceptance and operational handover each need evidence. “The website is online” does not establish that every preparation is complete.
AWS recommends an operational readiness checklist before launch to assess whether a team can operate and support a service, including processes, release quality and relevant requirements. We borrow the review method; AWS is not required, and this does not represent a certification. Source: Operational Readiness Reviews
Confirm one version and its opening scope
Record the release version, intended users and work scope first. Compare these with test and acceptance records for that version. Testing an earlier version does not establish that subsequent changes were checked. The team should also explain relevant differences between test and production environments.
List unfinished items as required for this release, confirmed for later, or unresolved. Users need to understand the alternative arrangements and limitations for deferred work. A daily process should not silently depend on something described as outside the first release.
Seven questions to establish a usable handover
- Who can start? Who enables accounts, checks work permissions and takes administration and support responsibilities?
- Where does the data come from? Which source and records are included, who checks completeness and accuracy, and how will users consult records not transferred?
- Which production connections are confirmed? If email or integrations are in scope, where are the production settings, intended senders and recipients, and verification results recorded?
- When does the new process take over? Who handles the switch window, closes the old entry point, processes final updates and notifies users?
- What triggers a pause? Which problems affect core work or data, and who can suspend access?
- What happens if work cannot continue? Have backup, recovery and temporary working arrangements been verified? How will new data created after the switch be retained and reconciled?
- Who helps after launch? Who owns reporting channels, agreed support hours, observation and the first review? Mark services not yet agreed as awaiting confirmation.
The business contact and team share these answers; clients need not write every technical document themselves. Each item needs an owner, evidence location and conclusion. Do not mark it complete without evidence.
Hypothetical example: moving project tracking out of Excel
This is a hypothetical example, not an actual client case. It does not mean the JunProjects website provides the following migration tools or service arrangements.
Suppose an event-planning team records projects in Excel and updates status through LINE. The first release only manages project ownership and progress. Existing attachments remain in agreed file locations.
Before switching, the parties could agree:
- The business contact identifies the final spreadsheet version and update cutoff. The team reconciles changes, and the business owner verifies them.
- After the approved switch window, users update progress through the new entry point. Agree how the old spreadsheet remains readable and how editing is restricted.
- Every open project has an owner. Include checks that attachment links remain accessible under the appropriate permissions.
- If core projects cannot be created or status cannot be saved, a designated owner decides whether to pause and use a verified temporary intake process.
- The business contact tracks references for new projects received through that temporary process and assigns responsibility for later entry. Reconcile before resuming normal work to avoid omissions or duplicates.
This does not promise zero downtime or silently add attachment migration to the first release. If another department still relies on the old spreadsheet, establish that dependency and its handling before deciding to switch.
A backup also needs a recovery plan
Ask the team for recovery-drill results and limitations: which version and data were tested, and how was usability checked after restoration? AWS also recommends actual recovery testing to verify data integrity and procedures rather than assuming a backup is usable. Source: Backup recovery testing
The business decides its acceptable interruption and data gap; the team assesses whether those objectives are achievable. Do not promise a fixed recovery time before testing. If returning to the old process, identify who retains, checks and re-enters data created since the switch.
Perform drills in an agreed safe environment. Deleting production data is not a way to demonstrate that a backup exists.
Finish with an actionable switch decision
Close the review with:
- Decision basis: Release version, scope, intended users and confirmation date.
- Required conditions: What was verified, what still blocks the switch, and who checked the evidence.
- Execution responsibilities: Who handles data, communication, switching and observation after launch.
- Pause and recovery: Trigger conditions, decision-maker, temporary process and reconciliation method.
- Conclusion: Proceed, or identify what must be completed before another review. Record this jointly with the authorized business contact and team.
A planned launch date does not replace incomplete essential checks. If assumptions change, update the arrangements and impact so users know which plan applies.
Start with: “We want to move project tracking into a system, but need to clarify old data, switching and post-launch responsibilities.” JunProjects’ AI PM can help organize requirements and initial estimates. The human team reviews and confirms formal scope, fees, delivery dates and cooperation arrangements. Explore custom software planning, or start a proposal by describing the work you plan to change.